Sound Transit 2 Line

2 Line between Bellevue and Redmond is HERE!

The entire East Link Extension includes 10 stations from Seattle's International District to Judkins Park, across I-90 to Mercer Island and South Bellevue, and through downtown Bellevue and the Bel-Red area to Redmond Technology Station. 

The 2 Line, between South Bellevue to Redmond Technology Station, is open as of April 27, 2024!

The remainder of East Link that connects the east side to the 1 Line in Seattle, is scheduled to open in 2025.

Facts

  • Open:​​​​​ 
    • South Bellevue Station to Redmond Technology Center: 2024
    • South Bellevue Station to International District/Chinatown Station: Scheduled to open in late 2025
  • Service: Every 8 minutes in peak hours when the 2 Line connects to Seattle. 
  • Travel times: Redmond Technology to Bellevue Downtown: 10 minutes

In August 2023, the Sound Transit Board voted for a phased approach to opening the East Link Extension, beginning with now-open 2 Line service between South Bellevue and Redmond Technology stations.

The remainder of East Link, that crosses I-90 and includes Judkins Park and Mercer Island Stations is expected to open in 2025.

 

 

 

Timelines and Milestones

    2008 Voter Approved

    2006-2011 Planning

    2011-2017 Designing

    2015-2024/2025 Construction

    2024-2025 Start of Service

 

Project Map

Watch the 2 Line!

 

 

Line 2 arrives on Lake to Lake
The latest Lake to Lake episode captures the excitement of light rail opening in Bellevue, with testimonials from delighted residents. Also on the show, a visit with the permit center, tips on preparedness from the Office of Emergency Management and a look at the new Safe Parking program. Read More